"Once a sleepy county road, Sam Bass Road has become a major transit alternative to I-35 to get traffic out of Round Rock and up to RM 1431," Williamson County Commissioner Terry Cook said in the county's announcement when the Sam Bass widening wrapped up on April 24, 2026. Six months later, on Oct. 22, Round Rock cut the ribbon on the Wyoming Springs Drive Extension. It's a four-lane divided road with a new bridge over Brushy Creek, and it runs between Creek Bend Boulevard and Old Settlers Boulevard.
Together, the two projects changed how traffic moves through the older neighborhoods west of I-35. If you're comparing homes in this part of Round Rock, the subdivision name tells you less than it did a year ago. Where the house sits relative to these two roads tells you more. That changes how a buyer should tour, and this fall's slower Williamson County numbers make those location details count at the negotiating table.
A bridge that was planned in 1999
Wyoming Springs has been in Round Rock's Transportation Master Plan since 1999. City Council approved the design contract in August 2019, and construction began in November 2024. The city's release puts the project at about $29.7 million. Round Rock and Williamson County shared the cost, using the city's Type B half-cent sales tax, certificates of obligation and the county's road bond program. "This project has been on the books for more than 25 years, and it's exciting to finally see it open to traffic," Public Works Executive Director Michael Thane said in the same release.
The bridge matters because Brushy Creek splits west Round Rock and there are few ways across it. The city's project page says the shortage of crossings sent north-south trips onto FM 3406, Sam Bass Road and RM 620 to reach I-35. Creek Bend Boulevard added one crossing when its extension opened on Jan. 3, 2017. Wyoming Springs is the second. The city expects it to take pressure off Sam Bass, Creek Bend and Old Settlers.
That's a projection. What can be measured is how much traffic was already there. The city's most recent count at Wyoming Springs and Brightwater Boulevard was 2,277 vehicles per hour at peak, and the city expects that to double by 2040. Its traffic model projected about 7,600 vehicles a day on the new segment at opening, rising to nearly 15,000 by 2040. That model assumed a 2023 opening, three years before the road actually opened.
The neighborhoods along the route
The city held two public meetings on the extension, on Sept. 1, 2020, and June 22, 2021, both at the Fern Bluff MUD Community Center. The city published the written comments and its answers in a master comment log, and those comments name the subdivisions closest to the road. Read today, they work as a map of who gained access and who gained traffic.
Stone Canyon is the largest neighborhood in Fern Bluff MUD, at roughly 1,100 homes. The district describes it as three miles west of Round Rock. Its HOA runs a Junior Olympic pool and play area. The MUD lists six parks, walking and biking trails and a community center that residents can use. In the 2020 comment log, Stone Canyon commenters described long waits turning from Wyoming Springs onto RM 620. They also worried about trees along Hairy Man Road and the more traffic the extension would bring.
Fern Bluff is the MUD's smaller namesake neighborhood, a deed-restricted community of 274 homes with access to the same district parks, trails and community center.
In Tonkawa Springs, some homes back up to the corridor the city had reserved for the road. Those residents raised noise, privacy and the new shared-use path behind their yards. The city replied that street trees were already in the plan and that it would consider more screening for noise.
North of Brightwater, residents of the Falcon-area subdivisions called Wyoming Springs their only practical way out of the neighborhood. The city pointed to Parkwood Valley and Oaklands as signalized alternatives. Sauls Ranch and the Whitewater Cove area also come up in the comment log as nearby.
| Area | How it relates to the 2026 road work | What to check on a showing |
|---|---|---|
| Stone Canyon | Wyoming Springs is a main way in and out, and the corridor now continues north over the creek | Wait times at the Wyoming Springs exits during the hours you'd actually drive |
| Fern Bluff | Shares Fern Bluff MUD's parks, trails and community center with Stone Canyon | Which exit you'd use toward Old Settlers or Creek Bend |
| Tonkawa Springs | Some homes back up to the new corridor and its shared-use path | Whether the lot backs onto the road, and what screening is in place now |
| Falcon area | Residents described Wyoming Springs as their main exit, with Parkwood Valley and Oaklands as signalized options | How the Wyoming Springs exit compares at peak with the signalized alternatives |
The same road can mean more traffic past one house and a shorter commute for the house two streets over. Look for the city's project map and the 2021 schematic on the project page. They'll show you which lots back up to the new four lanes more clearly than a listing photo will.
Sam Bass finished first
The county's Sam Bass Road/Corridor H project rebuilt Sam Bass between RM 1431 and Wyoming Springs Drive. It's now three lanes with a continuous center-turn lane, shoulders, intersection improvements and a shared-use path. Construction cost $36 million, funded by the 2019 voter-approved Williamson County Road Bond. The county's Corridor H fact sheet says the road was designed so it could someday widen to six lanes. No timeline or funding has been set for that.
If you're looking near Sam Bass, the road outside the house today is not necessarily the road it will always be. The six-lane design is already on paper.
There's one more project nearby. Round Rock is designing a roundabout at Sam Bass and Hairy Man Road. In its May 2026 update, the city said the public had favored the oblong, peanut-shaped option and that plans were at about the 60% stage. The project page lists an Oct. 8 open house where the city showed both roundabout designs. Expect construction at that intersection once design is done. If you plan to sell within a few years, that timing is worth factoring in.
Where the fall market comes in
For Round Rock, the most recent city-level figure is from August 2026. That month, Community Impact reported that the median sale price fell to $415,000 from $439,000 in August 2025, and sales were flat or down in all four Round Rock-area ZIP codes.
Countywide, the October 2026 numbers point the same way. Unlock MLS data published by KLBJ shows 720 Williamson County home sales in October, down 12.8% from October 2025. The median sale price was $375,250, down 9.2%. Months of inventory rose to 5.6. On average, homes sold in October for 92.6% of their list price, up from 91.8% a year earlier.
When homes close several points below list, the details that set two similar homes apart actually change the price. In west Round Rock right now, one of the biggest details is how a house relates to Wyoming Springs and Sam Bass. A 1990s home in Stone Canyon and another a mile away can look the same on paper. One may now have a faster route to Old Settlers, and the other may have four lanes and a shared-use path behind the fence. The price on each should reflect which of those two houses you're getting.
In practice, drive the route from a home you like at the hour you'd actually commute, both before and after the Brushy Creek bridge. Then compare that drive with one from a similar home on the other side of Wyoming Springs. If you're weighing a home as a rental, our Round Rock rental framework covers the other factors. For first-time buyers comparing price points across the city, see our starter-home guide.
FAQ
Is the Wyoming Springs Drive Extension open now? Yes. The city held the ribbon-cutting on Thursday, Oct. 22, 2026, and announced the segment between Creek Bend Boulevard and Old Settlers Boulevard was open to traffic.
Can you walk or bike across the new bridge? The extension has shared-use paths that connect to the existing Brushy Creek Regional Trail.
Will Sam Bass Road get wider again? Williamson County designed the rebuilt road so it could expand to six lanes later, but no timeline or funding has been identified.
What's planned at Sam Bass and Hairy Man Road? A roundabout. In its May 2026 update, the city said the public had favored the peanut-shaped design and that plans were at about 60%.
If you're considering west Round Rock this winter, we can help you compare specific houses by where they sit relative to Wyoming Springs and Sam Bass and what that should mean for your offer. Reach out to Better Broker, Texas Realty to talk through the houses on your list before you decide.